Broad objectives of the 14 week plan revised version of original 10-12 week plan
Project 1
Back of house main level
Complete concrete pads for deck and kitchen steps
Complete concrete path from kitchen steps to shed crushed stone gravel base for frost heave
Complete new concrete window well
Complete heavy flagstone approx 4" patio set in sand where wading pool used to be
Bonus heavy heavy flagstone approx 8" path between deck and kitchen
Bonus expand wildflower garden opp patio
Bonus grade and rotor till for grass seeding
Project 2
Back of house lower level
Lower ground level approx 3-4" to be below second back door level
Concrete drain surround lid and around back door allow for frost heave base on crushed stone and gravel
Install lower level deck on floating anchors and gravel supports
Complete heavy flagstone path between back doors and deck
Bonus expand wild flower garden opposite lower level deck
Bonus rotor till for grass seeding
Project 3
Front of house main level
Remove all railroad ties
Clean all interlocking brick re lay as single level
Add concrete step
Re grade side of house
Install light flagstone approx 1" patio on concrete
Bonus expand facing wildflower garden
Project 4 (in case it rains)
Strip basement laundry room and workshop and toilet
Project 5
Sow Wildflower seeds
Project 6 (if time)
Re shingle front roof
 |
Bottom pad completed |
 |
Excavating for path and window well |
 |
Window well forms in |
 |
Concrete pour completed for window well |